Method and assumptions
How Rischio calculates a pile and a group: units and conventions, the key assumptions, and the method from the shaft and the toe to uplift and lateral load.
The units, conventions and assumptions on this page hold on every page about piles.
Units and conventions
- SI units: forces in kN, stresses in kPa, lengths in m, unit weights in kN/m³, angles in degrees.
- Depth is measured down from the ground surface. The pile runs from its head at , 0 unless a buried cap sets it deeper, to its toe at .
- is the diameter of a circular pile or the side of a square one. Its perimeter is or , and its toe area or .
- The water table is at a depth below the ground surface, negative when water stands above it; kN/m³.
- is the vertical load on the cap, on the single pile or on the whole group, positive down; negative, it’s an uplift. A group’s cap may also take moments and , and the piles a lateral load at their heads, a single pile a moment there too.
Key assumptions
- Shaft and toe reach their ultimate resistance together: .
- The whole pile, from its head to its toe, carries shaft resistance.
- Pore pressure is hydrostatic below the water table and zero above it, so below it .
- Each stratum is uniform, with one or one . Drained strata carry no cohesion.
- The cap only transfers the load: it bears nothing on the soil, and its weight and the piles’ are not added to .
- What the designer leaves empty takes AASHTO’s value, in free mode too, and the trace of each check it moves says so:
- the pile’s modulus , by its material: 200 GPa for steel (29,000 ksi, 6.4.1); for concrete, Eq. 5.4.2.4-1 on a drilled shaft’s own or on 27.6 MPa (4.0 ksi: FHWA GEC 10 calls 3.5 to 5.0 ksi usual, §12.2.1, and its examples take 4.0), and on 34.5 MPa for a precast pile (5.0 ksi, AASHTO’s least at driving, 5.12.9.4.2); 10.3 GPa for timber (1,500 ksi, Southern Pine and Douglas Fir, Table 8.4.1.4-1). It moves a drilled shaft’s settlement, the piles’ compression in a group, and a pile under a lateral load;
- a sand’s , the slope of its p–y curve: AASHTO’s for the sand’s consistency (Lateral load);
- the depth to fixity of a steel pile that a flood’s scour leaves standing, which sets the column its structural check takes: Davisson and Robinson’s below the scour line, AASHTO’s for preliminary design (C10.7.3.13.4), in a clay, with , and in a sand, with the pile’s moment of inertia about its weak axis. In a group the soil’s modulus is lower the closer the piles stand: a quarter of it at three widths apart, all of it at eight (Prakash and Sharma, in the same commentary).
Method
The shaft resistance is added up stratum by stratum, by the data: a driven pile’s by Tomlinson’s α in an undrained stratum and Nordlund’s in a drained one, as FHWA recommends and AASHTO calibrates; a drilled shaft’s by FHWA GEC 10’s α and β. The toe resistance comes from the stratum the toe rests on: in clay; in sand, Nordlund’s for a driven pile and GEC 10’s for a drilled shaft. Each field says what it took and why. Their sum is the pile’s ultimate capacity, . A pile on its own is checked on ; a group is the sum of its piles and, with the toe in clay, can also fail as one block, and the weaker governs. A single drilled shaft’s settlement, by its load-transfer curves, and a group’s, as an equivalent footing over clays that consolidate and sands that settle by Hough’s method on their N60, are checked against the settlement the structure tolerates (Settlement); the ground that settles around the pile adds a drag load. A pile pulled up, by an uplift or by a moment on a group’s cap, is checked on its side, and a group also as one block (Uplift). Under a lateral load, the pile is a beam-column on p–y springs, and a group’s rows take AASHTO’s p-multipliers. Where Rischio has the section, a steel pile or a drilled shaft with its reinforcement, the pile’s structural resistance is checked in axial load, bending and shear. Free mode takes the same methods as AASHTO LRFD; along a drilled shaft, a sand’s is the one typed, where AASHTO takes it from the sand’s . Equations has every step, in the order of the calculation report.
References
- Das, B. M., & Sivakugan, N. (2019). Principles of Foundation Engineering, SI edition, 9th ed. Cengage Learning.
- Brown, D. A., Turner, J. P., Castelli, R. J., & Loehr, E. J. (2018). Drilled Shafts: Construction Procedures and Design Methods, FHWA-NHI-18-024 (GEC 10). Federal Highway Administration.
- Hannigan, P. J., Rausche, F., Likins, G. E., Robinson, B. R., & Becker, M. L. (2016). Design and Construction of Driven Pile Foundations, Vol. I, FHWA-NHI-16-009 (GEC 12). Federal Highway Administration.
- Nordlund, R. L. (1979). Point bearing and shaft friction of piles in sand. 5th Annual Short Course on the Fundamentals of Deep Foundation Design, University of Missouri-Rolla.
- O’Neill, M. W., & Reese, L. C. (1999). Drilled Shafts: Construction Procedures and Design Methods. FHWA-IF-99-025.
- Tomlinson, M. J. (1980). Foundation Design and Construction, 4th ed. Pitman, Boston.