A geotechnical report is a boring document unless you know what you are looking at. Most people who receive one are not soil engineers: they are structural engineers, developers, contractors, or owners who need one number out of it (the allowable bearing pressure, or whether the site needs piles) and have to trust the rest.
This guide is a map. It walks through what a geotechnical report contains, where each piece of information lives, and how the field and laboratory numbers feed the foundation recommendation. It ends with a worked example that takes a borehole log through the SPT and the bearing capacity to the number you would hand to the structural engineer.
You will not become a geotechnical engineer by reading this. You will be able to read a report without guessing, and you will know which results still belong to the geotechnical engineer to decide. For the field as a whole, from soil behaviour to foundations, walls and slopes, see what geotechnical engineering covers.
Units: quantities are given in SI (metric) with U.S. customary equivalents in parentheses — reading a report in either system is part of the job.
What a geotechnical report is and who writes it
A geotechnical report is a sealed engineering document prepared by a licensed geotechnical engineer (or firm) that summarizes the subsurface conditions at a specific site and translates them into design parameters and construction recommendations.
It is site-specific. A regional geology map tells you what is likely under your area; a geotechnical report tells you what was actually found under your lot, from borings, test pits, and laboratory tests done on your samples.
The report serves several readers at once:
| Who reads it | What they take from it |
|---|---|
| Structural engineer | Allowable bearing pressures, settlement estimates, foundation recommendation, seismic site class |
| Developer / owner | Feasibility, risk, and how site conditions affect cost |
| Contractor | Excavation support, dewatering, fill and compaction requirements |
| Building department | Documentation that the design accounts for the ground |
Because the readers differ, the report is structured into parts, and each part answers a different question.
The skeleton of a report
Most reports follow the same order. Once you know it, you can jump straight to the section you need without reading cover to cover.
- Introduction and scope — the project, the site, who authorized the work, and what the investigation was meant to answer.
- Site description — location, topography, drainage, neighboring structures, and any history of fill or grading.
- Field exploration — how many borings, to what depth, what sampling methods, and where they were located on a plan.
- Laboratory testing — which index and strength tests were run on the recovered samples.
- Subsurface conditions — descriptions of the soil and rock layers encountered, with depths and thicknesses.
- Groundwater — depths where water was encountered and any comments on seasonal fluctuation.
- Evaluation and recommendations — the soil parameters (sometimes a table), the foundation recommendation, fill/compaction, excavation, and any special hazards.
The two sections that do the real work are the borehole logs (where the field data lives) and the evaluation/recommendations (where the design numbers come from). The ones in between add context but rarely change a decision by themselves.
The boring log: the raw field data
The borehole log is the rawest piece of the report. Each boring gets a page showing, from top to bottom:
- Depth, in meters or feet.
- A soil description, with the USCS symbol for each layer (CL for lean clay, SP for poorly graded sand, and so on).
- Color, consistency, and moisture descriptors.
- Sampler type (SPT split spoon, Shelby tube, etc.) and recovery.
- In-situ test results, most commonly the SPT N-value (blows per foot or per 300 mm).
- Water level at the time of drilling.
The SPT N-value is the field test you will see most. A split-spoon sampler is driven with a 63.5 kg (140-lb) hammer falling 760 mm (30 in), and N is the number of blows for the last 300 mm (1 ft) of penetration (the first 150 mm (6 in) is seating, discarded). Higher N means denser, stronger soil.
Design does not use the field N as it is. First it is corrected for the energy the hammer delivers, , with the energy ratio in percent. Some correlations also normalise it for the overburden pressure, , and others do not: each correlation is used with the N it was built on. Skimming the raw log instead of the parameter table is where this goes wrong.
From N-value to bearing pressure: the parameter table
Good reports collect the derived soil parameters in a single table in the evaluation section. Look for it. It typically lists, per layer:
- Friction angle and/or undrained shear strength
- Unit weight
- Modulus or a settlement-related parameter
- Allowable bearing pressure (sometimes given directly)
If the report gives the allowable bearing pressure for a shallow foundation outright, that is usually the number the structural engineer needs, read with two things beside it: whether it is gross or net (gross vs net bearing pressure), and the footing width it was computed for. If the report gives parameters instead, the capacity has to be computed, as in the worked example below.
Reading the recommendation section
The recommendations tell you what type of foundation the geotechnical engineer expects to work. The main possibilities:
| Recommendation | What it means for the design |
|---|---|
| Spread footings at depth X with allowable pressure Y | Shallow foundation on competent soil; you size footings against Y |
| Mat / raft foundation | Soil too variable or weak for individual footings; the slab spreads the load |
| Deep foundations (piles, drilled shafts) | Competent soil is too deep or too weak near the surface; carry load deeper |
| Ground improvement then shallow | Improve the soil (e.g. stone columns, dynamic compaction) so a shallow foundation works |
When the recommendation is deep foundations, the report usually gives the pile type, the estimated length, and an allowable capacity per pile (geotechnical only, not structural). That feeds directly into a pile capacity calculation.
Settlement: the silent governor
A footing can have a huge factor of safety against bearing failure and still be a failure because it settles too much or, worse, settles unevenly. On clay especially, settlement often governs before bearing capacity does.
The report should give expected total settlement and, if the layout is sensitive, differential settlement. Two numbers matter:
- Immediate (elastic) settlement for granular soils, which happens as the load is applied.
- Consolidation settlement for clays, which happens slowly as water drains out of the pore spaces over months or years.
If the report says the settlement is “within tolerance,” check what tolerance it used, because the limit depends on the type of structure. The limits and the calculation are in foundation settlement.
A worked example: from a boring log to an allowable pressure
The report for a light structure has one boring, BH-1, to 6 m (≈ 20 ft), with no groundwater down to its bottom. A square footing 1.20 m (≈ 3.9 ft) wide will be founded at 1.00 m (≈ 3.3 ft), in the silty sand of the first layer. The report gives parameters but no allowable pressure, so it has to be computed: the chain a structural engineer runs when the report stops short of a final number.
| Depth (m) | Material | USCS | SPT N (blows/300 mm) |
|---|---|---|---|
| 0.0 to 1.5 | Silty sand, medium dense | SM | 12 |
| 1.5 to 4.0 | Poorly graded sand, medium dense | SP | 22 |
| 4.0 to 6.0 | Poorly graded sand, dense | SP | 38 |
The report’s parameter table gives the silty sand = 30°, = 0 and = 18 kN/m³ (≈ 115 lb/ft³).
Step 1: correct N for hammer energy. The report says a safety hammer with = 60 % was used, so .
Step 2: the pressure that gives 25 mm of settlement. Meyerhof (1956) correlated the SPT with the net pressure that settles a footing on sand by 25 mm (≈ 1 in), and Bowles (1977) proposed a modified, less conservative form. For m:
with in kPa and in mm. is the blow count of the soil between the base and below it, with no overburden correction. Here that zone runs from 1.00 to 3.40 m and holds N of 12 and 22; taking the lower one is on the safe side:
Step 3: bearing capacity. With Terzaghi’s equation for a square footing and his factors for = 30°, = 22.46 and = 19.13 (Das and Sivakugan, 2019, Table 6.1), and the overburden = 18 × 1.00 = 18 kPa:
With a factor of safety of 3, on the net basis so it compares with step 2:
Step 4: the design value. Bearing capacity governs, 183.9 kPa against the 306.0 kPa of settlement. The value for the structural engineer is about 180 kPa net (≈ 3.8 ksf), 198 kPa (≈ 4.1 ksf) on the gross basis. At that pressure the same correlation gives the settlement:
within the 25 mm.
Terzaghi’s equation has no depth or shape factors on the overburden term. The general bearing capacity equation, the one Rischio’s bearing capacity calculator works out, has them, and for this footing it gives = 793.3 kPa (≈ 16.6 ksf) and a net allowable of 258.4 kPa (≈ 5.4 ksf), still below the 306.0 kPa of settlement. The method is part of the value, so the report should say which one it used.
Red flags on the page
Some findings in a report should stop the conversation, not just adjust a number:
- Fill without proper compaction data. Fill that was placed without testing is suspect under a footing no matter how clean it looks.
- Organic soils or peat in the foundation zone. They are compressible, often deeply so, and consolidate for years.
- Groundwater above or near the bearing level, especially if the report does not address dewatering or buoyancy.
- Loose or soft blow counts, an of 10 or less in sand (loose or very loose) or 4 or less in clay (soft or very soft), in the top few metres under a loaded footing, or low blow counts that the report “explains away.” The classes are Peck et al.’s (1974), in FHWA’s Soils and Foundations manual, Table 3-9.
- Expansive clay listed for the bearing stratum. Seasonal shrink-swell moves footings independent of load.
- A “log of test pits” but no in-situ or lab strength data — you have a description, not a design parameter.
When you see any of these, the report should have already proposed a mitigation (deeper footing, piles, ground improvement, moisture control). If it documents the hazard but does not resolve it, that is a gap to raise with the geotechnical engineer, not a detail to skate over.
How much a report costs and why
The cost depends on the region, the number and depth of the borings, the laboratory program and how fast you need it. Groundwater monitoring, deep borings, seismic site-class work or contaminated-ground evaluation all add to it, so a quote is only comparable with another for the same scope of exploration.
What you are paying for is the parameters the structural engineer needs, and the opinion of a licensed engineer on a site you cannot see. Skimping here by ordering fewer or shallower borings does not save money in the end: it just moves the risk and the cost into the foundation, where changes are expensive.
Frequently asked questions
Do I always need a geotechnical report? For any structure that transfers meaningful load to the ground, yes in practice. Many jurisdictions require one for permitting on new construction. For small, light, and well-understood structures in stable ground, some codes allow a default assumed bearing pressure, but that is a risk decision, not a technical one.
What is the difference between a factual and an interpretive report? A factual (or data) report presents the field and laboratory results without interpretation. An interpretive report adds the engineering evaluation and recommendations. Most projects need the interpretive version; the factual one is sometimes used for design-build where the design team does its own reading.
How deep do the borings need to be? Enough to reach the stratum the foundation will bear on plus the zone of influence below it, and deep enough to catch soft layers that settlement could mobilize. The geotechnical engineer sets this from the project loads and the site.
Can I use the SPT value directly to pick a bearing pressure? Only as a first approximation, in sands, with a correlation like the one in step 2 and the N corrected the way that correlation asks for. When a report gives you its own allowable pressure, use that number.
Putting it together
Reading a geotechnical report is pattern recognition, not a geotechnical degree. Find the boring logs, find the parameter table, check the recommended foundation and the allowable pressure, check whether settlement was addressed, and watch for the red flags. When the numbers are not in the report, they have to be computed honestly (with the settlement check, not just a capacity formula), and the tools on this site can run the bearing and settlement checks with every parameter in view.
The worst possible way to use a geotechnical report is to skim it for the highest allowable pressure and design against that. The people who built the report built it so you would not have to guess.
Sign up free and run your first foundation check.
References
- Das, B. M., & Sivakugan, N. (2019). Principles of Foundation Engineering, 9th SI ed., Cengage: Table 6.1 (Terzaghi’s factors) and Section 9.6 (Meyerhof’s and Bowles’s correlations).
- Samtani, N. C., & Nowatzki, E. A. (2006). Soils and Foundations, Vol. I, FHWA-NHI-06-088: Table 3-9 (relative density and consistency from ).
- Meyerhof, G. G. (1956). “Penetration Tests and Bearing Capacity of Cohesionless Soils”. Journal of the Soil Mechanics and Foundations Division, ASCE, 82(SM1), Paper 866.