Warnings
Every warning Rischio can raise on a pile or a pile group, keyed by its code: what it means and its level, and what each check can suppose.
A warning flags something unusual in this result: data that don’t fit together, a value at the edge of a method’s range or chart, a calculation that didn’t converge, or a physical condition the numbers show. Results marks each one as danger, caution or information: one about a check on that check’s page, one about the whole model under Notes. The calculation report lists them too. Each entry below carries the engine’s code, the one an answer from the API or the MCP gives.
Capacity
Unusual friction angle
Caution · unusual_friction_angle
A stratum’s is above 45°: possible in rock fill, rare in soil, and often a typing error. The calculation runs, and the warning points at the stratum.
A wide pile for Nordlund
Caution · nordlund_wide_pile
The pile is wider than 24 in. (0.61 m), where FHWA GEC 12 (p. 232) says Nordlund’s method tends to overpredict the shaft resistance: confirm it with a load test or another method.
The toe's φ′ below Nordlund's limit chart
Information · nordlund_limit_below_chart
The toe stratum’s is below where AASHTO’s chart of the limiting unit toe resistance starts (Fig. 10.7.3.8.6f-9). Rischio carries the chart’s first slope on, which lowers : the safe side, since caps the toe resistance.
A clay past Tomlinson's chart
Caution · tomlinson_beyond_chart
A clay’s is beyond the last value of AASHTO’s Fig. 10.7.3.8.6b-1, and its α holds the curve’s last value (Shaft resistance). FHWA GEC 12 suggests API’s α for highly overconsolidated clays.
A sand's OCR taken as 1
Information · drilled_shaft_ocr_floored
For a drilled shaft’s β, a sand’s comes from its where it isn’t given (AASHTO Eqs. 10.8.3.5.2b-4 and -5). Here that correlation gives below 1, which a soil can’t have, so β takes the OCR as 1, normally consolidated, as FHWA GEC 10 holds it (App. A, Tables A-4 and A-5).
Piles closer than the minimum
Caution · pile_spacing_below_minimum
The piles of a group are closer than the least spacing their rule reaches, and the warning shows on the group’s capacity. A driven group, in any soil and either mode, takes AASHTO’s minimum, the greater of 30 in. (0.76 m) and 2.5 widths (10.7.1.2). AASHTO sets no minimum for a drilled shaft group (10.8.1.2), so under AASHTO it takes where the group factor it reads by its spacing starts: 2.5D in a clay soft at the surface (10.7.3.9, by 10.8.3.6.2), and in sand 2D for a single row and 2.5D for several (Table 10.8.3.6.3-1). Closer than that, is the one at the start of its table.
Block failure governs
Caution · block_failure_governs
Only with the toe in clay, : the group as a block carries less than its piles on their own, so the block sets (Pile groups). A wider spacing enlarges the block.
Settlement and negative skin friction
Settlement past the load transfer
Caution · settlement_above_load_transfer
No movement of the drilled shaft carries its working load: the load is past what its side and its tip mobilize on AASHTO’s load-transfer curves, so the settlement isn’t computed.
Negative skin friction
Caution · downdrag
The ground settles around the pile and drags it down with the drag load , the pile’s own side above the neutral plane (AASHTO 3.11.8; Negative skin friction). It loads the pile’s structure and adds to its settlement; its geotechnical resistance doesn’t take it (10.7.1.6.2).
The neutral plane in a settling stratum
Caution · neutral_plane_in_settling_stratum
The neutral plane is above the bottom of a stratum that settles, so the pile settles with that stratum there. AASHTO aims the plane at competent soil (C10.7.2.3.1): a longer pile takes it down.
A clay above the equivalent footing
Information · consolidation_above_equivalent_footing
The neutral plane puts the group’s equivalent footing below a clay that consolidates. AASHTO places the footing at or below the plane (10.7.2.3.1), so that clay’s consolidation isn’t in the group’s settlement.
Uplift
No block into rock
Information · group_uplift_block_in_rock
The piles reach rock: the group has no block of soil to lift, and the sum of the piles’ uplift resistances governs (Uplift, AASHTO 10.7.3.11).
The block weighs its soil
Information · group_uplift_block_soil_only
The group’s block weighs its soil alone, the piles in it counted as soil (FHWA GEC 12, §7.2.3.2.2). AASHTO’s also takes the cap (Eq. 10.7.3.11-2), whose weight is in the load’s dead part (Uplift).
Lateral load
The p–y solution didn't converge
Danger · p_y_not_converged
The pile on its p–y springs didn’t settle on a deflection: the pile may be too short to hold the load, or the load past what the soil can take. Its deflection and moments aren’t reliable.
Structural resistance
A depth to fixity not used
Information · depth_to_fixity_unused
You gave a depth to fixity, and no flood’s scour leaves the pile standing free above the ground, so nothing reads it: a pile fully in the ground doesn’t buckle (Structural resistance, AASHTO 10.7.3.13.1).
Longitudinal steel outside AASHTO's limits
Caution · aashto_longitudinal_steel_ratio
The drilled shaft’s longitudinal steel ratio is below (no more than 1.5 % is asked) or above 8 % (AASHTO 5.6.4.2). The structural checks still run on the cage given.
Too few or too small bars
Caution · aashto_longitudinal_bars
AASHTO asks a round column at least six longitudinal bars, none smaller than #5 (5.6.4.2), and the shaft’s cage has fewer or smaller.
A spiral below AASHTO's ratio
Caution · aashto_spiral_ratio
The spiral’s or the hoops’ volume ratio is below AASHTO’s (Eq. 5.6.4.6-1), with no more than 75 ksi.
What a check supposes
What a method or the code assumes isn’t a warning: Results says it on the page of each check it moves, under What it supposes, and the calculation report beside that check. These are the ones a pile’s checks can say.
The pile's modulus, by its material
pile_modulus_by_default
The pile’s isn’t given, so it takes AASHTO’s for its material: 200 GPa for steel (6.4.1), its concrete’s by Eq. 5.4.2.4-1, and 10.3 GPa for timber (Table 8.4.1.4-1) (Method and assumptions).
A sand's k by its consistency
subgrade_gradient_by_default
A sand along the pile has no subgrade modulus , so its p–y curve takes AASHTO’s for its consistency by , dry above the water table and submerged below it (Table C10.4.6.3-2; Lateral load).
The depth to fixity by Davisson and Robinson
depth_to_fixity_by_default
The depth to fixity below a flood’s scour line isn’t given, so the pile’s column takes Davisson and Robinson’s, AASHTO’s for preliminary design (C10.7.3.13.4). A soil–structure analysis gives the pile’s own (10.7.3.13.4).
The cap's passive resistance left out
cap_lateral_resistance_not_counted
A buried cap’s passive resistance isn’t counted against the lateral load, the safe side (AASHTO 10.7.3.12).
No side in a cohesive intermediate geomaterial
igm_side_not_counted
A drilled shaft’s length in a cohesive intermediate geomaterial, from 0.48 to 4.8 MPa (10 to 100 ksf, AASHTO C10.8.2.2.3), carries no side resistance: Rischio doesn’t compute an IGM’s side (FHWA GEC 10, §13.3.5.4), the safe side. Its tip is the rock’s.
A rock socket's side and tip together
rock_socket_side_and_tip
The side in rock and the tip are counted together, the side taken as ductile (AASHTO 10.8.3.5.4d). Strain softening is rare in rock sockets; where it’s expected, its residual strength comes from tests.
Bending without the axial load
aashto_axial_flexure_not_combined
Under AASHTO, a pile whose section Rischio doesn’t compute, a precast concrete or timber pile or a drilled shaft without its cage, is checked in bending against the yield moment given, under bending alone. AASHTO’s lateral strength limit is the section’s combined axial and flexural resistance (C10.7.3.12): check that interaction in the pile’s structural design.
The settlement's load factor, the owner's
aashto_settlement_gamma_by_owner
AASHTO sets the load factor on a settlement, , for Hough’s and Schmertmann’s methods and for consolidation (Table 3.4.1-5). For a drilled shaft’s settlement by its load-transfer curves (10.8.2.2.2) it’s the owner’s to set: Rischio takes 1.00, as for a footing’s elastic settlement, to be confirmed with the owner.