FHWA-NHI-16-064, Example D.10.2, D.13 · H-pile in uplift
H-pile in uplift, Example D.10.2, D.13 of FHWA-NHI-16-064, solved in Rischio. Nominal uplift resistance, Rs: 95.3 kips (source: 94.0 kips).
SourceManual
Hannigan, Rausche, Likins, Robinson & Becker (2016). Design and Construction of Driven Pile Foundations: Comprehensive Design Example (FHWA-NHI-16-064). Federal Highway Administration. Example D.10.2, D.13, p. 28, 51-52.
ID fhwa-nhi-16-064-north-abutment-uplift-28ft
Rischio isn't affiliated with the source's authors or publishers. If you hold its rights and want this example removed, write to hello@rischio.io.
The problem
What the source calculates: nominal uplift resistance, Rs. Its problem, as Rischio's editor opens it under AASHTO LRFD 10th (2024):
Source vs Rischio
| Source | Rischio | Difference | |
|---|---|---|---|
| Nominal uplift resistance, Rs | 94.0 kips | 95.3 kips | +1.3 % |
Opened in the studio under AASHTO LRFD 10th (2024), the model passes every check.
The manual's shaft resistance comes from the DrivenPiles program, and Rischio reads Nordlund's coefficients off AASHTO's charts, so the two can differ by up to 2 %. The model carries the pull on a pile of the back row (Tables D-13 and D-14), which Rischio factors to 37.6 kips, where the manual's Strength I gives 46: the 28 ft pile holds either, as in the manual (Table D-16).
How it's calculated
- Uplift →How Rischio checks piles pulled up: each pile's load under a moment on the cap, a single pile's side resistance, and a group as its piles or as one block.
- Pile groups →How Rischio checks a single pile and a pile group: the group as individual piles or as one block, Skempton's factor in clay, and the group efficiency.
- Equations →Every step of the calculation, in order.
- Piles in Rischio →The tool: what it checks, and its calculation report.
Nearest examples
- FHWA-NHI-16-064, Example D.10.1, 60 ft · H-pile in gravelFederal Highway Administration (2016): shaft resistance, Rs
- FHWA-NHI-16-064, Example D.11 · Each pile's load in a groupFederal Highway Administration (2016): load on the most loaded pile
- FHWA-NHI-06-089, Example 9-2 · Precast pile in silty sandSamtani & Nowatzki (2006): ultimate capacity, Qu